- The quick answer
- What changed in November 2025, and what didn't
- Who needs a factory licence now
- How to get a factory license: the steps
- Factory licence fees: two state schedules and a worked example
- A worked example
- Factory licence, manufacturing licence and the other permissions
- After the licence: renewal, amendments and the duties that come with it
- Where the factories are: Starleads' manufacturing data
- Related industry lists
- Selling to factories: what they buy and the rules for reaching them
- Questions people ask
- How to get a factory license in India?
- Are a manufacturing license and a factory license the same?
- What is the purpose of a factory license?
- Is a factory license mandatory for MSMEs?
- What is the new factory licence limit under the labour codes?
- Do I have to get a new licence because of the OSH Code?
- How much is the factory licence fee?
The quick answer
A factory license (factory licence in Indian official English) is the permission a state's factories department, usually called the Directorate of Industrial Safety and Health or the Chief Inspector of Factories, gives a premises to run a manufacturing process with workers. Since 21 November 2025 the law behind it is the Occupational Safety, Health and Working Conditions Code, 2020 (the OSH Code), which replaced the Factories Act, 1948. Under the Code a premises is a factory, and needs the licence, when 20 or more workers work there and a manufacturing process runs with power, or 40 or more without power. The old thresholds were 10 and 20. You apply online to your state, after getting the factory's plans and site approved, and pay a fee set by the state on a slab of workers and horsepower. Until a state notifies its new rules, its old Factories Rules, forms and fees still apply.
Below: who needs the licence now, what the labour codes changed, the steps, two real state fee tables with a worked example, how it differs from other permissions, and where factories are in Starleads' data. Every rule was read on official pages on 18 November 2026, linked where used.
What changed in November 2025, and what didn't
The Government announced that the four labour codes, including the OSH Code, were "being made effective from 21st November 2025", replacing 29 older labour laws. The same PIB press release of 21 November 2025 added the sentence that matters most for anyone applying today: "During transition, the relevant provisions of the existing labour Acts and their respective rules, regulations, notifications, standards, schemes, etc. will continue to remain in force." In practice, your state's Factories Rules, application forms, fee schedule and portal keep working until the state notifies its own rules under the Code.
The text of the Code itself (Act 37 of 2020, which we read in the Gazette copy published by PRS Legislative Research) sets out the new frame. Section 143 repeals the Factories Act, 1948 along with 12 other laws, including the Contract Labour (Regulation and Abolition) Act, 1970. Most pages ranking for "factory license" still describe the old Act, so here is what is new:
| Point | Factories Act, 1948 (repealed) | OSH Code, 2020 (in force from 21 Nov 2025) |
|---|---|---|
| When a premises is a factory | 10 or more workers with power; 20 or more without power | 20 or more workers with power; 40 or more without power (section 2(1)(w)), unless a state law already in force set a different number |
| Where the licensing power sits | Section 6 and each state's Factories Rules | Section 79 (state rules on plans, site permission, licensing, renewal and fees) and section 119 (a common licence) |
| Plan and site permission | Prior permission from the state or Chief Inspector; deemed approval rules varied | If no order comes within a period of up to 30 days on an online application with plans, the permission is deemed granted (section 79(2)) |
| Licence decision | Timelines set by state rules and service-guarantee laws | Licence issued electronically within 45 days, or deemed issued and auto-generated (section 119(4)) |
| One licence or several | Separate licences for a factory and for each contractor engaging contract labour | One common licence can cover a factory, beedi and cigar premises and engaging contract workers, or any one of them (section 119(1)) |
| Contract labour licence | Contractors with 20 or more contract workers | Contractors with 50 or more contract workers, according to the PIB note on the OSH Code of 22 November 2025 |
| Licences already held | n/a | Valid for the period they were issued for, then to be obtained afresh under the Code (section 119(5)) |
| Inspection | Inspectors | Inspector-cum-Facilitators, randomised web-based inspection and third-party audit for some establishments (PIB note) |
The PIB note also counts what the Code cut: 13 Acts into one, 4 licences into 1, 6 registrations into 1, 21 returns into 1 and 84 registers into 8. It adds that a first offence punishable only with a fine can be compounded by paying 50% of the maximum fine. How fast each state gets there depends on its rules.
What did not change: you still need the licence before manufacturing starts, and the state still issues it and sets the fee. Some states have already published OSH rules: Puducherry's labour department, for example, lists a "Puducherry Occupational Safety, Health and Working Conditions Rules, 2026 - Preliminary Notification" dated 27 August 2026 on its site. Check your state labour department's notifications page before you file.
Who needs a factory licence now
Three tests decide it, and all three come from section 2(1)(w) and 2(1)(zi) of the Code.
- Is a manufacturing process carried on? The Code's meaning is wide. It covers making, altering, repairing, finishing, packing, oiling, washing or cleaning any article with a view to its use, sale, transport or disposal; pumping oil, water or sewage; generating or transmitting power; printing of every kind, from letterpress and offset to 3D printing and book binding; building or breaking up ships; and "preserving or storing any article in cold storage". A packing unit, a printing press, a job-work shop and a cold store can all be factories.
- How many workers? 20 or more on any day of the preceding twelve months if the process uses power; 40 or more if it doesn't. All workers in a day count together, in every shift and relay, so two shifts of 12 make 24.
- Does a state law set another number? The Code's own proviso says that where a state law in force before the Code set a different number, the state's number prevails in that state until its legislature amends it. States could amend the Factories Act for themselves, and some did over the years, so read your own state's position (its labour department or factories directorate states it) before deciding you are below the line.
Three exclusions and one catch. The definition leaves out hotels, restaurants and eating places, railway running sheds and mobile units of the armed forces. A computer or data processing unit does not make a premises a factory if no manufacturing process is carried on there. The catch is section 81: a state may, by notification, apply the factory provisions to any place where a manufacturing process is carried on, whatever the number of workers. Hazardous processes are the usual reason.
Falling below the factory threshold does not take you out of the Code. Section 2(1)(v) defines an "establishment" as a place where any industry, trade, business or manufacturing is carried on with ten or more workers, and section 3 says every new establishment must apply online for registration within 60 days of the Code applying to it. So a unit with 14 workers and power was a factory under the old Act; under the Code it needs a registration, not a factory licence, unless its state's numbers or a section 81 notification say otherwise.
| Your unit | Under the old Act | Under the OSH Code (subject to state law) |
|---|---|---|
| 8 workers, machines on power | Not a factory | Not a factory, and below the 10-worker establishment line |
| 14 workers, machines on power | Factory: licence needed | Establishment: online registration under section 3; no factory licence |
| 25 workers in two shifts, on power | Factory | Factory: licence needed (20 or more with power) |
| 30 workers, handwork only, no power | Factory (20 or more without power) | Establishment, not a factory (below 40 without power) |
| 45 workers, handwork only | Factory | Factory: licence needed |
| Any size, in a hazardous process the state has notified | Could be declared a factory under section 85 of the old Act | Can be declared a factory under section 81 of the Code |
How to get a factory license: the steps
Every state runs its own portal (often inside its single-window system for investors), so screens and form numbers differ. The order of work is the same everywhere. The Puducherry labour department's factory page is one of the clearest official descriptions online, and we use it as the example; your state's page will look similar.
- Check whether you are a factory. Count workers across all shifts, list the power you will connect in horsepower or kW, and apply the three tests above. If you are below the line, register as an establishment instead.
- Prepare the plans. A site plan, building plans with cross-sections and elevations, the machinery layout and a flow chart of the manufacturing process, signed by the occupier. Puducherry asks for plans in triplicate with Form I-C.
- Apply for site and plan approval before you build or extend. This is the permission in section 79(1)(b) of the Code. Puducherry's list of documents: the paid scrutiny fee challan (₹100 for small, ₹500 for medium and ₹1,000 for large units), the plans, the registration certificate from the industries department, the land or building document, the process flow chart and a description of each stage, the previous occupier's details and licence cancellation if the building was a factory before, the partnership deed or memorandum and articles, and the pollution control NOC for hazardous industries. Under the Code, if no order is communicated within the period the state sets, up to 30 days, the permission is deemed granted.
- Get the stability certificate. A competent person (a structural engineer approved by the state) certifies that the building is safe for the machines and loads. Puducherry's licence form must be accompanied by it.
- Collect the other clearances your process needs. Usually the consent to establish from the State Pollution Control Board, a fire NOC from the state fire service for larger or risky buildings, and boiler registration if you run a boiler (see the next sections).
- Apply for the licence and pay the fee. In Puducherry the application is Form-2 with the stability certificate and the fee challan. Other states use their own form numbers. Under section 119 of the Code you may ask for a common licence covering the factory and the engagement of contract workers together.
- Wait for the decision. The Code requires the licence to be issued electronically within 45 days, or it is deemed issued and auto-generated; if it is refused, the reason must be given, and you can appeal within 30 days.
- Keep it current. Display the licence at the factory, apply to amend it before you raise the workers or horsepower beyond the licensed limits, change the factory's name or change the occupier or manager, and renew it before it expires.
Ask your state portal whether it has moved to the Code's common licence yet before you pay a consultant. The Udyam registration and GST registration usually come first, because states ask for the industries department or Udyam certificate with the plans.
Factory licence fees: two state schedules and a worked example
There is no national fee. Each state's rules set a grid of horsepower installed against the maximum number of workers on any day of the year. Two official schedules we read today show how much they differ.
The Delhi Labour Department's fee chart under Rule 5 of the Delhi Factories Rules, 1950, in force since 1 January 2001, charges per year:
| Horsepower installed | Up to 20 workers | 21 to 50 | 51 to 100 | 101 to 250 | 251 to 500 | 501 to 750 | 751 to 1,000 | Above 1,000 |
|---|---|---|---|---|---|---|---|---|
| Nil | ₹100 | ₹200 | ₹400 | ₹1,000 | ₹1,600 | ₹3,000 | ₹4,000 | ₹5,000 |
| Up to 10 | ₹200 | ₹400 | ₹480 | ₹1,200 | ₹2,400 | ₹3,600 | ₹4,800 | ₹6,000 |
| Above 10, up to 50 | ₹400 | ₹600 | ₹800 | ₹2,000 | ₹4,000 | ₹6,000 | ₹8,000 | ₹10,000 |
| Above 50, up to 100 | ₹800 | ₹1,000 | ₹1,200 | ₹3,000 | ₹6,000 | ₹9,000 | ₹12,000 | ₹15,000 |
| Above 100 | ₹1,200 | ₹1,600 | ₹2,000 | ₹4,000 | ₹8,000 | ₹12,000 | ₹16,000 | ₹20,000 |
Delhi lets a factory take the licence, or renew it, for one, five or ten years, paying the yearly fee times the number of years. Each amendment (change of occupier, address, name, number of workers or horsepower) costs ₹100, and a duplicate licence ₹100. The page says the fee is deposited with a GAR-7 treasury challan at SBI, Old Secretariat.
Puducherry's schedule, in force since 18 October 2002, uses finer slabs, more of them, and runs much higher at the top: from ₹200 a year for a unit with no power and up to 9 workers, to ₹1,08,000 for one above 10,000 HP with more than 10,000 workers. Renewal costs the same as the grant and must be applied for at least two months before expiry; a late renewal costs 10% extra if filed at least a month before expiry, 20% within the last month and 30% after expiry. An amendment costs ₹5 and must be applied for 15 days ahead; a duplicate licence costs ₹50.
A worked example
Take a sheet-metal unit with 30 workers over two shifts and 40 HP of machines. Under the Code it is a factory (20 or more workers, with power).
- In Delhi: the row "above 10, up to 50 HP" and the column "21 to 50 workers" give ₹600 a year, or ₹3,000 for a five-year licence.
- In Puducherry: the row "above 10 HP up to 50 HP" and the column "up to 50 persons" give ₹1,200 a year, plus the plan scrutiny fee (₹100 for a small unit) when the plans go in.
The licence fee is rarely the big cost; the stability certificate, drawings, other clearances and any consultant usually cost more. A state that notifies its OSH rules may change its schedule, so check the portal on the day you pay.
Factory licence, manufacturing licence and the other permissions
People searching "factory license" often mean any permission to start making things. The factory licence is one of several, issued by different authorities for different reasons, and none replaces another.
| Permission | Who issues it | What it is about | Who needs it |
|---|---|---|---|
| Factory licence | State factories department (DISH or Chief Inspector of Factories) | The premises and the safety, health and welfare of the workers in it | Premises meeting the factory definition: 20+ workers with power or 40+ without, subject to state law |
| Establishment registration under the OSH Code | State registering officer | Recording the establishment and its workers, including inter-state migrant workers | Establishments with 10 or more workers |
| Consent to establish and consent to operate | State Pollution Control Board or Committee | Air and water pollution from the site | Most manufacturing units, by the board's category of the industry |
| Fire NOC | State fire and emergency service | Fire safety of the building | Depends on the state's fire law, building height, area and the hazard |
| Product licence ("manufacturing licence") | The regulator for that product: drug controller, FSSAI, BIS, PESO and others | The product itself and its quality | Makers of medicines, food, ISI-mark goods, explosives and other regulated products |
| Trade licence | Municipality or panchayat | Using that address for that trade | Most businesses in a city's trade schedule |
| Udyam and GST | Ministry of MSME; GST department | MSME status; indirect tax | Udyam is voluntary but useful; GST above the turnover limits or for inter-state supply |
So a pharmaceutical tablet unit with 60 workers needs a factory licence for the premises and a drug manufacturing licence for the tablets; our drug license guide covers the second. A food processor needs an FSSAI licence on top of the factory licence (see our FSSAI license check), and a factory in a city usually needs a trade license from the municipality too. A cold store with 20 or more workers is a factory under the Code's definition, which our cold storage business guide covers along with its subsidies.
Shops and offices fall under the state's shops act instead (see our shop and establishment registration guide); a unit that only trades never needs a factory licence.
After the licence: renewal, amendments and the duties that come with it
The licence is the start of the factory's obligations, not the end. The common ones, under the old rules and the Code alike:
- Renew on time. Validity is set by the state: one year in many, with options of five or ten years in Delhi. Late renewal costs a surcharge (10% to 30% in Puducherry). Under section 119(5) of the Code, a licence issued under the old Act stays valid until it expires and must then be taken afresh under the Code.
- Amend before you grow. The horsepower and the number of workers on the licence are limits. Adding machines or a third shift beyond them, renaming the factory or changing the occupier needs an amendment first.
- Report changes and closure. Section 3 of the Code asks an establishment to report changes in ownership, management or particulars within 30 days, and to report closure, with a certificate that workers' dues are paid, within 30 days of closing.
- Keep the registers, file the return and report accidents as the state's rules require.
- Form a safety committee if the factory has 500 or more workers.
- Re-approve plans when you extend. Replacing a machine, or adding one without reducing safe clear space or worsening heat, dust or fumes, is not an extension under section 79; a new shed or floor is.
Each of these is a buying moment for suppliers: a new shift means more safety gear, an extension means engineers and contractors.
Where the factories are: Starleads' manufacturing data
State factories departments do not publish full, current lists of licensed factories with contact details. Starleads holds contacts for the manufacturers that need these licences, compiled from business directories. The counts below were checked on 18 November 2026; they are counts of contacts in Starleads' data, not an official census and not a register of licensed factories.
- Manufacturers & Manufacturing Companies (All Industries): 3,27,598 manufacturers across 35 states and 1,290 cities, 78% with a mobile number and 50% with an email. The most are in Maharashtra (92,057), Delhi (38,643) and Gujarat (37,933); by city, Mumbai (59,284), Delhi (27,211), Bengaluru (25,470), Pune (16,687) and Hyderabad (10,970). By industry, the biggest groups are machinery, tools and engineering (85,061) and steel, metals and castings (34,960).
- Industrial Machinery & Equipment: 87,958 makers and dealers in 284 cities, 81% with a mobile; Maharashtra has 32,332 of them.
- Steel, Metals & Minerals: 1,42,930 contacts, 88% with a mobile and 81% with an email.
- Chemicals, Plastics & Rubber: 77,756 contacts, 79% with a mobile. Chemical units are the ones most often in hazardous processes, with the extra site appraisal that brings.
- Packaging & Printing: 64,524 contacts. Printing is named in the Code's definition of a manufacturing process, so larger presses are factories too.
- Fabricators & Engineering Works: 34,183 contacts, 91% with a mobile, many of them small job-work units right at the new 20-worker line.
- Fire Safety & Fire Fighting Equipment: 2,570 suppliers, 83% with a mobile, for factories looking for the other side of the fire NOC. Our Insights page has the industry and city totals behind these lists as a CSV.
Live figures: our Manufacturers & Manufacturing Companies (All Industries) list has 3,27,598 contacts in 1,290 cities, 78% with a mobile number and 50% with an email. Every list page has 60 sample rows to download free before you pay.
Related industry lists
- Manufacturers & Manufacturing Companies (All Industries) 3,27,598 contacts · 50% email · 78% mobile ₹1,999
- Industrial Machinery & Equipment 87,958 contacts · 40% email · 81% mobile ₹1,999
- Fabricators & Engineering Works 34,183 contacts · 41% email · 91% mobile ₹1,999
- Chemicals, Plastics & Rubber 77,756 contacts · 67% email · 79% mobile ₹1,999
- Fire Safety & Fire Fighting Equipment 2,570 contacts · 62% email · 83% mobile ₹499
Where Starleads falls short: the lists give a business's name, contact person where listed, phone, email, address and the industry it makes for. They do not say whether a unit holds a factory licence, how many workers it has, its horsepower or its licence number, so they help you find and reach manufacturers, not check their compliance. For a supplier check, use the GST, MCA and Udyam look-ups in our company search guide, and ask the factory for a copy of its licence. City, state and specialisation lists cost ₹499 and all-India files of 10,000 or more contacts ₹1,999, plus 18% GST. Our manufacturing companies list guide and machinery manufacturers guide go deeper into those markets.
Selling to factories: what they buy and the rules for reaching them
For safety equipment makers, fire contractors, structural engineers, compliance consultants and payroll software firms, the OSH Code is a reason to talk to factories this year: thresholds moved and licences are renewed under the new law as they expire.
- Sell to the right person. In a small factory the owner decides; in a larger one the plant head handles the licence, HR the registers and contract labour, and the safety officer the audits and PPE.
- Lead with the date that matters to them. Licence expiry, a planned extension, or the state's notification of its OSH rules. "Your licence was issued under the Factories Act; when it expires it has to be taken afresh under the OSH Code" is a useful opening, and true under section 119(5).
- Check DND before calling. Many owners of small units use a personal mobile for the business. TRAI's rules under the Telecom Commercial Communications Customer Preference Regulations, 2018 let people block promotional calls and SMS through the National Customer Preference Register (NCPR); scrub numbers first, as our DND check guide shows, and honour every request to stop.
- Register for bulk SMS. Business SMS in India goes through DLT: the sender, the header and every template must be registered with a telecom operator before sending, as our DLT registration guide explains. Promotional messages need consent or must avoid numbers on the DND register.
- Email is the gentler first touch: send small batches from an authenticated domain, with an easy opt-out.
Starleads sells business contacts only. It does not sell lists of factory workers or other private individuals, and a factory's workers are not a market for cold calls.
Questions people ask
How to get a factory license in India?
Check that your unit is a factory (20 or more workers with power, or 40 or more without, unless your state's law says otherwise), get the site and building plans approved by the state's factories department, get a stability certificate from an approved structural engineer, collect the pollution and fire clearances your process needs, then apply online on your state's portal with the fee. Under the OSH Code the licence must be issued within 45 days or is deemed issued.
Are a manufacturing license and a factory license the same?
No. The factory licence is about the premises and the workers' safety, issued by the state's factories department. A "manufacturing licence" usually means a product licence from the regulator of that product, such as a drug manufacturing licence, an FSSAI licence or a BIS licence. Many units need both.
What is the purpose of a factory license?
It lets the state check, before work starts, that the building is stable and the layout safe, and puts the factory on the inspectors' records. Its limits on workers and horsepower bring the factory back to the department before it grows.
Is a factory license mandatory for MSMEs?
MSME status has nothing to do with it, and Udyam registration does not replace the licence. A micro unit with 25 workers on power machines needs one under the Code; a medium unit that only trades does not.
What is the new factory licence limit under the labour codes?
20 workers where the manufacturing process uses power and 40 where it doesn't, up from 10 and 20 under the Factories Act. A state's own number prevails where its law set a different one before the Code, and a state can notify any premises as a factory regardless of size.
Do I have to get a new licence because of the OSH Code?
Not straight away. A licence obtained under the old law is deemed to be under the Code and stays valid for the period it was issued for; it has to be obtained afresh under the Code when it expires.
How much is the factory licence fee?
Each state sets its own grid of horsepower and workers. In Delhi it runs from ₹100 a year for a unit with no power and up to 20 workers to ₹20,000 for one above 100 HP with more than 1,000 workers; in Puducherry from ₹200 to ₹1,08,000. Check your state's current schedule on its portal.